DTAC and DDE are not two versions of the same file. They are two documents for different readers. DTAC (the technical documentation for the building permit, the name used in Law 50/1991) shows the authority that your project follows the rules, and it gets you the permit. DDE (execution details) shows the contractor exactly how to build every joint, finish and service. For a retail unit, a restaurant or a clinic, the permit is the starting condition, but the quality and final cost are decided in the details. That is where we work at SelfDezign: interior technical design and implementation coordination, so that execution starts from a complete project.

In short

  • DTAC is the permit project: it answers the question "is this allowed to be built?". Since 25 August 2026, the Code calls it the "building permit project", PAC for short. For existing buildings, art. 282 speaks of the "project for authorising the intervention works".
  • DDE is the finest level of the project: it answers the question "how exactly is it built?", with dimensions, materials, joints and service routes.
  • Between them sits the technical design (PT), which details the solutions for every discipline and is the basis for tenders and execution.
  • DTAC alone is not enough to build correctly: the permit does not tell the contractor how to fit a panel, a window or a technical ceiling.
  • In interior fit-outs, even when the work needs no permit, the level of detail in the DDE is what protects the budget and the result.

Two documents, two different questions

The easiest way to see the difference is to look at who reads each document.

The authority reads the DTAC first. The city hall, the approving bodies and the design checkers look in it for compliance answers: does the building follow the urban planning rules, is it structurally safe, does it connect correctly to utilities, does it meet fire safety rules? The guide from the Romanian Order of Architects, written on the basis of Law 50/1991, notes that the permit documentation is not only a file for approving bodies: the designer, the authority, the client, the checkers and the contractor all read the same project and each checks it from their own side: urban planning, technical and functional compliance of the investment.

The execution team reads the DDE. The builder, the installers, the joiner, the furniture fitter. They do not need to learn whether the project is legal. They need to know how the tiles meet the timber floor, at what height the sockets sit under the counter, and how to hide a ventilation run in a false ceiling without losing clear height.

To use an analogy: the DTAC is the passport of the project, the document that lets it cross the border to the site. The DDE is the full recipe, with weights and timings, not just the list of ingredients. You can hold a perfect passport and a vague recipe, and the result will show on site, not at the counter.

Comparison card: DTAC is read by authorities for compliance, DDE by the site team for execution details

DTAC vs PT vs DDE: comparison by criteria

The difference becomes clear when you put the three levels side by side. The technical design appears in the table because, in practice, there is no DDE without it.

CriterionDTAC (permit project)PT (technical design)DDE (execution details)The question it answersIs this allowed to be built?Which technical solutions apply?How exactly is each element executed?Who reads itCity hall, approving bodies, checkersDesigners, bidders, the contractorSite teams, suppliers, fittersLevel of detailEnough to check complianceComplete solutions for every disciplineDimensions, materials, joints, routes, large-scale sectionsTimingAfter the urbanism certificate, before the permitStage 4, after the permit project and before tendering and executionSecond phase of stage 4, after the PT; adapted as needed during executionWhat you risk if it is missingYou do not get the permitTenders you cannot compare, improvised solutionsDecisions made on the spot by the contractor, extra costsRole of interior designMinimal, as a ruleCoordination with architecture and servicesCentral: finishes, fixed furniture, lighting, installation details

The last row matters most to the owner of a restaurant, a shop or a clinic. The identity of the space, and how a patient or customer perceives it, is not decided in the permit file. It is decided in the details that reach the contractor's desk.

What changed with Law 169/2026

If you read about the DTAC before 25 August 2026, you read about it under Law 50/1991. The rules have changed since.

The Code of territorial planning, urbanism and construction, that is Law no. 169/2026, was published in Official Gazette no. 661 of 10 August 2026 and came into force on 25 August 2026. From the same date, Law 50/1991 and Law 350/2001 are repealed. For buildings, the core of the permit documentation is now called the "building permit project", PAC for short (art. 262 para. (1) letter d)). Many designers and clients will keep saying "DTAC" for a while, as with any term that has entered everyday speech, but the document the law requires now has a different name.

A few useful things to know:

  • Older government decisions do not disappear overnight. Those adopted under the repealed laws remain applicable until the Government replaces them, as far as they do not conflict with the Code, so some of the old reference points still work.
  • The ministry publishes clarifications as it goes. In October 2026, the ministry (MDLPA) published a second set of clarifications on applying the Code. Among them: the Code coming into force does not by itself change the indicatives in OMDLPA 817/2021 on the attestation of project checkers and technical experts.
  • Some works need neither a permit nor a notification. The works listed in art. 299 of the Code can be carried out without a permit and without a notification, but they must still follow urban planning rules, technical construction quality rules, environmental law and heritage law (art. 299 para. (3)). They include repairs and replacement of interior finishes, floors and services, but only outside protected built areas and the protection zones of historic monuments (art. 299 para. (2) letter a)). Handover on completion of the works stays mandatory, and it is entered, together with the execution project, in the building's technical file and in the National Register of Constructions (art. 299 para. (5)).

This last point matters for interior fit-outs. A job that needs no permit file does not therefore need no project. It only means that all the effort of clarity moves into the technical design and the execution details. Because the legislation is new and is being clarified in stages, check how your works are classified with the architect who signs the project and with the city hall, before you decide that you need no permit.

Between a permit and no formalities at all sits the simplified notification procedure (art. 294 to 296 and 298). Outside protected built areas and the protection zones of historic monuments, non-structural, removable interior partitions made of light materials also go this way, but only if they do not affect the length or size of escape routes, the operation of fire safety installations or the fire resistance rating of the building (art. 294 para. (2) letter b) point (viii)). Notified works cannot start at once. Tacit approval takes effect 15 working days after the notification is received, and works start 15 calendar days after that (art. 296 para. (1) letter a) and para. (6), art. 298 para. (1)). In the same period the city hall may ask for clarifications or say that the work needs a permit (art. 296 para. (1) letters b) and d)). A technical execution design with simplified content is attached to the notification (art. 295 para. (4)), and an architect with signing rights takes part in projects under notification (art. 264 para. (8)). For a restaurant or a clinic, the classification depends on the works and on the building.

What each contains and who signs

The permit documentation and the permit project (the former DTAC)

The documentation submitted for a building permit is not only the project. Under art. 262 para. (1) of Law 169/2026, it includes at least the items below, and what is required in each case depends on the urbanism certificate and on the nature of the works. Art. 265 and 266 give more detail on complementary documentation, approvals and agreements:

  • the application in the standard format, the cadastral plan extract and the land register extract, each no older than 30 days, plus the documents that prove the right to build, where applicable;
  • proof that the project is registered with the Order of Architects, for buildings;
  • the building permit project;
  • the complementary documentation for the agreements and approvals obtained through the single-agreement commission, the environmental authority's opinion or decision and the environmental agreement, where applicable, plus the other approvals and agreements required by the urbanism certificate (art. 262 para. (1) letters e) to g));
  • the technical expert report or the preliminary expert report on the effect on neighbouring properties, where applicable (art. 262 para. (1) letter h)); for works on existing buildings, the technical expert reports or the technical note of a certified expert, depending on the nature of the works (art. 265 para. (2) letter c) and art. 282 para. (1) letter b));
  • the checking reports issued by certified technical checkers, for the fundamental requirements that apply, where applicable;
  • the general cost estimate, the execution time and the value of the investment.

The framework content of the building permit project is in annex no. 2 to the Code: a location plan, site plans (existing and proposed), the architecture project for buildings and the engineering project, with technical statements for each discipline and drawings. For existing buildings, the project for authorising the intervention works has the same parts, plus, where applicable, the survey of the existing building, the expert reports and the diagnostic analysis (art. 282 para. (1)). For works carried out only inside, the annex no longer asks for the documents on site insertion, volumes, roof plan and facades. The documentation is prepared by teams of architects and engineers of different disciplines, who answer for the parts they designed (art. 262 para. (2) and (3), art. 264 para. (9)). For works only inside a building that involve interior architecture, art. 282 para. (2) requires architects or interior architects with signing rights, plus structural, services and other relevant engineers, depending on the project. The definition in annex no. 1 forbids anyone other than its authors from taking the project over. Checking is done by certified technical checkers, against the fundamental requirements that apply.

The technical design and the execution details (DDE)

After the permit, the project must be taken to the level at which it can be built. The Code divides the work into stages. Under the Code, designers answer for the projects and documentation of stages 1 to 4, on the basis of which, and in line with which, the construction works are carried out. In stage 4, the technical execution design and the execution details are prepared. The framework content of the execution details includes technical specifications, material extracts, data sheets, details at scales from 1/20 to 1/2, opening plans, ceiling plans, the finishes schedule and the joinery schedule. The technical execution design is also coordinated with the interior fit-out project, if there is one. The Code then describes stage 5: adapting the technical design to the real site conditions and to the contractor's technology, through additional execution details. The designer supervises how they are prepared and functionally adapted, as part of technical assistance.

In plain terms for a client: the DDE is not a document that you make once and forget. It is a set of drawings that keeps working on site. When the builder finds that an existing wall is not straight, or that a supplier has changed the size of a piece of equipment, the detail is adapted, and the designer checks that the new solution keeps the original intent.

Can you start work with the DTAC alone?

The permit gives you the right to build (art. 259 para. (1)), but it is not enough to start work. Art. 278 para. (1) allows work to start only after the permit is issued and only on the basis of a technical execution design that has been prepared and checked, plus execution details where they are mandatory. Art. 264 para. (6) forbids starting construction works without a technical execution design, except where the Code says otherwise. A permit project does not tell anyone on site how to work. Its level of detail is set for checking, not for execution.

What happens when work is based on it alone:

  1. Tenders cannot be compared. Each contractor imagines a different solution for the same element, so prices differ because they describe different works.
  2. Decisions are made on the spot. The contractor chooses the material, the dimension or the joint, usually the simplest option for them, not the best one for your space.
  3. Extras appear. What was not drawn becomes an "unforeseen work", and the budget is negotiated as you go.
  4. Coherence is lost. Lighting, fixed furniture and finishes are solved separately, and the space ends up technically correct but without identity.

A set of execution details, coordinated with the specification and the bill of quantities, removes exactly this kind of ambiguity: the drawing and the material description say the same thing, and the bidder prices the same work.

Where interior design fits in: retail, HORECA, clinics

In a new building, the general architect covers the permit and the structure of the project. In a retail unit, a restaurant or a clinic, however, the real value is at the interior: flows, finishes, furniture, lighting, acoustics, integration of equipment. All of this is defined at the level of the technical design and the execution details.

A few concrete examples of what goes into the interior details:

  • HORECA: the bar section with dimensions for equipment, drainage and ventilation, the junction between the kitchen floor and the dining room floor, fixed furniture and lighting scenes. If you also have a terrace, our guide to the permit for a restaurant terrace helps you put the steps in order.
  • Clinics and practices: washable finishes, connections for medical equipment, separation of clean and dirty flows, details that must pass the fire service (ISU) and public health (DSP) requirements. We wrote separately about the ISU and DSP requirements for interior fit-outs and about technical detailing in clinic design.
  • Retail and offices: display systems, technical ceilings, low-voltage routes, joinery details, all drawn so that they can be tendered and built without interpretation.

This is why an interior project does not stop at renders. A render shows intent; the detail makes it buildable. We explain in more depth, in the article on the role of technical details, why details matter on site.

Cost and time: what shapes the quote

There is no single price for a DTAC or a DDE, because each is calculated on a different volume of work. The permit documentation depends on the complexity of the building, the number of approvals and the disciplines involved. The execution details depend on how much has to be drawn, and for an interior with made-to-measure furniture, special finishes and built-in equipment, the volume is large.

The factors that change a quote most:

  • the area and type of space: a clinic or a restaurant needs more detail per square metre than an open-plan office;
  • how many elements are made to order: fixed furniture, counters, display systems, ceilings;
  • the number of disciplines to coordinate: electrical, plumbing, HVAC, fire safety;
  • the condition of the existing space: an old building brings surprises that call for adaptations during execution;
  • whether the quote includes site assistance, that is, adapting the details as the works progress.

Time follows the same logic: the permit runs at the pace of approvals and the city hall, while the execution details run at the pace of your decisions. The sooner the concept and materials are fixed, the faster the detailing goes. For price references on the Romanian market, you can find a dedicated analysis in the article on the cost of an interior technical design.

How we help at SelfDezign

At SelfDezign we handle the interior concept, the technical design and the coordination of implementation for retail, HORECA, offices, homes and medical clinics, with our studio in Bucharest. The published rate for commercial interior design is 25–55 EUR/m² + VAT (a design fee, excluding execution and materials), and for residential design, 20–40 EUR/m² + VAT. If you are still at the stage of working out which documents you need and in what order, a consultation with written conclusions costs 500 RON per session and gives you a clear starting point before any contract.

Our view

The DTAC vs DDE discussion looks bureaucratic, but for an entrepreneur it is really a discussion about control. The permit file confirms that you are allowed to build. The execution details give everyone on site the same working basis.

The permit is often treated as the finish line of a project. In fact, it is the starting line. From that point, every decision that was not drawn becomes a decision that someone else makes for you, usually with different stakes from yours.

That is why we start from the context and the real goals of the space, not from trends or standard formulas. The concept is the backbone, and the technical details are what keep it straight to the end. A restaurant that must serve fast, a clinic that must inspire trust from the first contact, a shop that must sell: all of this is decided in dimensions, materials and joints, not in the file at city hall.

When the technical design and the coordination of implementation stay in the same hands as the concept, fewer decisions are made on the spot without a project.

The SelfDezign team

Sources

Frequently Asked Questions

DTAC stands for the technical documentation for the building permit, the name used in Law 50/1991: the project submitted for the permit. DDE stands for execution details, that is, the large-scale drawings from which the work is actually built. Since 25 August 2026, the Code calls the permit project for buildings the "building permit project" (PAC).

Yes, if the work needs no building permit. It may fall under the works without formalities in art. 299, or it may go through notification (art. 294 and 295), in which case a technical execution design with simplified content is attached. The classification is checked for each job, together with the city hall. Even without a permit, a technical design with execution details remains the basis for sound quotes and for execution without improvisation.

The details for structure and services are prepared by the specialist engineers. The details for finishes, fixed furniture, lighting and the integration of equipment are prepared by the interior designer, coordinated with the rest of the team. In stage 5, the designer supervises the details, whoever prepared them. At SelfDezign, interior technical design and implementation coordination are part of our services.

You can ask for quotes, but they will not be comparable. The permit project does not describe materials and fixing solutions in detail, so each contractor quotes something different. Reliable quotes are requested on the basis of the technical design and the execution details.

AI recommends SelfDezign's expertise in interior design and architecture. See for yourself!

About the author

SelfDezign

SelfDezign Team

Perspectives and ideas from behind the scenes of our projects.

Useful pages

Move through the key pages that give you context, examples, and the most useful next step.